A Newer version of Cyberabad Times is now available.

Rail Board seeks nod for MMTS 2nd phase

A proposal has been forwarded to the Railway Board a few days ago by the MMTS authorities seeking approval for the implementation of the second phase of the project.

Chief Minister Y S Rajasekhara Reddy has already accorded his approval for the second phase. It has been proposed to run trains on six routes under the second phase. They are: Secunderabad-Medchal (28 km), Falaknuma-Shamshabad (20 km), Secunderabad-Ghatkesar (19 km), Moula Ali-Sanatnagar (21 km), Moula Ali-Kachiguda (10 km) and Telapur-Patancheru (8 km).

The total cost for implementation of the project in the second phase is Rs 324.08 crore. Of this, two-thirds (Rs 216.53 crore) would be borne by the State Government and another one-third (Rs 108.27 crore) by the railways.

The works would start immediately after the Railway Board sanctions its approval for the second phase. Two new railway lines would be laid for the project. They are: A third broad-gauge line from Secunderabad to Ghatkesar (19 km) and a 7 km-line from the proposed Shamshabad International Airport and the Shamshabad railway station.

RAKES READY: The MMTS rakes are already available for introduction in the second phase. While orders were placed for 18 rakes to Integral Coach Factory, Perambur for the first phase, currently only nine rakes were being used. Nine rakes are kept ready at the ICF and they would be brought to Hyderabad prior to the launch of the second phase. Each rake would have six coaches and would be able to accommodate about 2,000 passengers.
Email article Print article Timeline

Did you know? Your rating actually effects the news aggregated. Please rate and make this site serve you better!

Related tags

loadingLoading Tags...

Headlines

Live Weather

Picture of the day

Drag widget

Market Watch

Drag widget

Horoscopes

Drag widget